Perseus Mining Ltd's (ASX:PRU) development works at the Yaouré Gold Project in Cote dIvoire are 52% complete and are tracking on schedule and budget for first gold production in December this year.

Yaouré remains on schedule to achieve the stretch target of first gold pour, subject to no COVID-19 related delays, thus becoming the company's third operating West African mine.

The company has released a new video revealing progress at the site.

It shows drone footage of the mine site under construction and outlines construction progress showcasing the primary crusher, reclaim tunnel, water services ponds, ball and SAG mills, CIL tanks, HV switchyard, tailings storage facility as well as the river abstraction and powerline corridor.

The companys two producing gold mines, naRead More – Source